13th Apr 2009 | 02:13 pm | Filed under Blog, Home Plan Series
The construction of the Camas plan by Gansen Construction for our clients Mr. & Mrs. C is moving along quite nicely. This week the foundation was poured and floor joists set. Framing is about to begin and trusses are scheduled for delivery April 23rd.